Description
Bardi Water Filling Line for 18.9L or 5 gallon bottles speed 600 bph
Manufacturer: BARDI – Italy
Model: VICTORIA 5G LS 340-13-29-3R
Year of manufacture: 2006.
Capacity: 600 bph
Bottles come already labeled by the packaging manufacturer
Line Composition:
Automatic cap remover
- Device with own control cabinet and conveyor belt
- Bottle pressure test device – micro-crack control
- Device with own control cabinet and conveyor belt
- Bottle washing machine with 4 stages of washing
- Prewash with cold water
- Washing with hot water 60 ° C and detergent (brushes for external washing of bottles)
- Bottle disinfection
- Rinsing with ozone-enriched water
- It is possible to use alkaline and acidic agents
Monoblock with fillers and capper
Device with conveyor, 3 fillers in the water filling line and automatic capper with the option of rinsing each stopper with ozone. Filling the default volume via a volume meter.
- Pneumatics: Asco and Rexroth
- Printer – LINX 4900 – printing the date on the product
- Device for placing sleeve foil around the bottle cap
- Manufacturer – CLEVER – Italy, 2009
- Output conveyor – conveyor belt only
Main control cabinet with touch panel
Full line management (BARDI equipment)
The line is equipped with SIEMENS PLC control devices – Touch panel SIEMENS TP170B MONO – SIEMENS MICROMASTER 420
Water treatment technology – offered separately
There is a complete technology for water treatment (reverse osmosis, mineralizer, ozonator and other ancillary equipment.
There is a buffer tank, stainless steel 3000 L (Contact tank O3, part of water treatment equipment).
Complete technical documentation, wiring diagrams, instructions for handling and maintenance, manual with all spare parts (including order code) and service maintenance records.
Line Maintenance
The line, including all accompanying technology, is regularly maintained and as such ensures safety in the processes for which it is intended. General inspection and preventive maintenance of the complete line was done twice a year, and every month control and disinfection of the line.
Replacement of worn parts (bearings of electric motors, conveyors, washing brushes, drive of washing brushes, pneumatics, packaging grippers, electric solenoid / pneumatic valves )
Lubrication(pneumatic cylinders, bearings, conveyor sliders)
Washing and disinfection (mechanical washing, alkaline washing twice a year, fine cleaning of all elements and disinfection once a month of the complete line).
General Information
The required space for the Used Bardi Water Filling Line, including the manipulative space is approximately 180 m2. The required height of the hall is 5-6 m.
The line records the total number of filled packaging, now 4.3 million bottles in 14 years of operation with 16 hours per day on average.
Required installed power in kW for the complete equipment:
Electric power consumers | EL.SNAGA |
UAT – Water preparation | 30 kW |
R. BARDI 600 – Washing machine and filler | 117 kW |
CLEVER-Sleeve aplicator | 7 kW |
Caps elevator | 0,20 kW |
Compressor | 7.5 kW |